This project is located in Aydın, Turkey. It was completed and commisioned in 2012. I was the acting project and construction manager for this 63 MWe Natural Gas Fired Combined Cycle power plant.
Some of the key figures and critical items are follows;
45.000 m2 landplot
GE LM-6000 PC Sprint NG Turbine + Generator
Aalborg Heat Recovery Steam Generator
GE Thermodyn 6-7 MC9 14.150 kW Steam Turbine + Generator
SPIG Water Cooling Tower
NG PRMS Station
11.5 kV / 154 kV Grid connection works
Water treatment plants (demineralized water productio plant + pre-filtration plant)
Raw Water / Fire Water Reservoirs
Water wells
Technical and Administrative Building
Plant SCADA and DCS Systems
Plant Fire Protection Systems
Overall plant Electromechanical Balance of Plant